A contractor assigns a task to two workers, A and B. Worker A can complete the work in x days, while worker B takes 5 days more than A. Working together, they can finish the task in 6 days. Find the value of x.

Last updated Jul 21, 2026
Correct Answer: Option C — 10
1. Define Daily Work Rates
Worker A completes the task in x days, which means worker A completes 1 over x of the task per day.

Worker B takes 5 days longer, which is x plus 5 days, meaning worker B completes 1 over x plus 5 of the task per day.

Working together, they finish the task in 6 days, making their combined daily work rate 1 over 6.

2. Combine Rates and Simplify
Adding their individual daily rates together gives 1 over x plus 1 over x plus 5, which equals 1 over 6.

Combining the left side over a common denominator gives two x plus 5 over x squared plus 5 x, equal to 1 over 6.

Cross-multiplying to eliminate the fractions gives 6 times two x plus 5, which equals x squared plus 5 x.

Expanding the left side gives 12 x plus 30 equals x squared plus 5 x.

Moving all terms to one side gives the quadratic equation: x squared minus 7 x minus 30 equals 0.

3. Solve for x
Factoring this equation yields x minus 10 times x plus 3 equals 0.

This provides two possible values for x: 10 or negative 3.

Since time in days cannot be negative, x must be 10.

Conclusion
Correct Answer: C) 10
Answer verified by Quintessence Classes faculty — Karan Nagar, Srinagar.

About this question

JKSSB Social Forest Worker 2026

Details

Exam JKSSB
Recruitment Social Forest Worker
Year 2026
Subject Maths
View all questions from this paper

More Maths questions

From across UPSC, JKPSC, and JKSSB papers — same subject, different years.

Practice 2,543+ more PYQs interactively

Filter by subject, year, and exam in real time. Get instant feedback, detailed explanations, and track your progress.

Open practice portal